MAIN STREET PAVING UPDATE
This coming Monday 6/4 through Wednesday 6/6 there will be daytime pavement milling work from Hoyt St. to the northern City limits.
Starting on June 10 or 11 there will be nighttime work for the first coat of pavement from Hoyt St. to the northern City limits.
Meanwhile, daytime driveway work and work in the road on valves and sewer/stormwater accesses will continue along the project corridor.
Updates will be posted www.facebook.com/CityofSaintAlbans and other venues.
The primary project contact is Jacqueline Dagesse, jdagesse@eivtech.com, (802) 497-3653.
The City contact is Chip Sawyer, c.sawyer@stalbansvt.com, (802) 524-1500 x*259.