Paving_Update_05-17-18.png
Click on image to view larger size

MAIN STREET PAVING UPDATE

On Monday the 21st, daytime operations (starting 4:30 AM) are planned between Stebbins St. and the Twigg's bump-out. On-street parking will not be available during this time, and traffic will be two-way where possible, but otherwise flagged.

On Tuesday the 22nd, daytime operations (starting 4:30 AM) are planned between the Twigg's bump-out and Hoyt St. On-street parking will not be available during this time, and traffic will be two-way where possible, but otherwise flagged.

Monday and Tuesday's work will begin at 4:30 AM and end in the afternoon.

May 23 - 25 there will be work on side streets from Diamond to Hoyt. Impacts to Main Street will just be focused on the intersections.

From May 29 to June 1, night work (6 PM to 6 AM) is planned to apply the first coat of pavement from Diamond to Hoyt.

This is the current plan, and we will get the word out if there are changes. Please monitor City of Saint Albans for updates.

Project contacts are: Jacqueline Dagesse, jdagesse@eivtech.com, (802) 497-3653 and Chip Sawyer, c.sawyer@stalbansvt.com, (802) 524-1500 x*259.

Thank you.